The progress of the cricket net extension at Chelsea Recreation Reserve is tracking well. It has taken a while to get to this point and it is great to see it actually happening.

Work Completed This Week – 

• Completed installation of retaining wall
• Completed installation of 20mm crushed rock base to both the additional wicket and Vmax 50 boundary runoff
• Begun Sanding and preparation of existing fence rails and posts
• Installed timber edging for vmax 50 runoff
• Saw cut and remove concrete for new dividing net posts

Week Look Ahead (including, but not limited to) – 

• Complete installation of fence posts for additional practice bay
• Complete preparation and pouring of concrete slab 
• Complete Sanding and preparation of existing fence rails and posts
• Commence painting of all existing fence rails and posts 

Target Completion Date – 

Practical Completion 28th August 2020.